
Utility Projects
See how Orbital supports your ability to deliver safe, reliable and affordable energy solutions to your communities.
Utilities
138kV Generation Line Interconnection
Transmission Line Engineering
138kV Generation Line Interconnection
Transmission Line Engineering
Overview
- Location: Indiana
- Client: Midwest investor-owned utility
- Timeline: 12 months
Scope
- Designed 138kV generation tie line to connect into existing substation in PLS-CADD.
- Designed a temporary configuration for the 138kV feeder line to maintain power while substation expansion occurred.
- The final configuration comprised of three engineered monopoles and one engineered H-Frame on foundations.
- Plan and Profile Drawings, Framing Drawings, Load Tree Drawings, Foundation Design Drawings, Stringing Charts, Staking Tables, Worklists, and Material Lists
More Projects
Utilities
138kV Substation Expansion
Substation Engineering
Featured
345k Double Breaker Interconnect Substation
Construction Management
Utilities
Management Programs
Construction Management
Utilities
Inlet/Outlet Valve Evaluation
Natural Gas
Utilities
Odorant Replacement Project
Natural Gas
Featured
Federal Funded Maintenance Program Management
Natural Gas
Utilities
Department Of Transportation (DOT) Project
Electric Distribution Engineering
Department Of Transportation (DOT) Project
Electric Distribution Engineering
Scope of Work
- Construction design for the relocation of existing 25kV sub-transmission and 15kV distribution overhead utilities to accommodate Department of Transportation (DOT) highway modifications and widening
- Coordinated with Department of Transportation (DOT) and other utilities for phased construction approach
- Facilitated and obtained private right of ways for new utility structures and easements
- Completed forestry efforts
- Designed demolition of existing facilities and distribution equipment
- Provided engineering support for highway rated underground utility designs
Deliverables
- Site visits to scope and assess constructability of relocations
- Produce a detailed design and construction package (cost estimate, design sheets, design maps, bill of material, circuit diagram, and material reservation using client work management application)
- Coordinate easement and permit research and secure permits with local and state jurisdiction
- Create and distribute construction packets
- Provide design support during construction
Project Highlights
- Orbital upheld all Department of Transportation (DOT) cost and schedule commitments throughout this multi-year effort, which began prior to 2020 and continued through COVID-era restrictions. When the utility partner faced internal resource limitations, Orbital stepped in to provide critical design and engineering support, keeping the project on track and maintaining construction momentum.
More Projects
Utilities
138kV Substation Expansion
Substation Engineering
Featured
345k Double Breaker Interconnect Substation
Construction Management
Utilities
Management Programs
Construction Management
Utilities
Inlet/Outlet Valve Evaluation
Natural Gas
Utilities
Odorant Replacement Project
Natural Gas
Featured
Federal Funded Maintenance Program Management
Natural Gas
Utilities
34kV Breaker Replacement Program
Substation Engineering
34kV Breaker Replacement Program
Substation Engineering
Scope of Work
- Replace four 34kV circuit breakers
- Adaptation to re-use existing foundation
- Replace seven disconnect switches
- New cable trench
- Upgrade bus differential relaying and transformer relaying
Deliverables
- Detail design and construction package
- Drawings – demolition, protection and control, physical, civil and structural
- Review vendor drawings for breakers, disconnect switches, and cable trench
- Material procurement support
- Construction support
- Incorporate as-built drawings post-construction
Project Highlights
- Orbital Engineering provided full engineering services for the breaker replacement program, including management of multiple sites, coordination of equipment ordering, and completion of required protection upgrades.
More Projects
Utilities
138kV Substation Expansion
Substation Engineering
Featured
345k Double Breaker Interconnect Substation
Construction Management
Utilities
Management Programs
Construction Management
Utilities
Inlet/Outlet Valve Evaluation
Natural Gas
Utilities
Odorant Replacement Project
Natural Gas
Featured
Federal Funded Maintenance Program Management
Natural Gas
Utilities
Utilities and Internet Service Providers
Joint Use Make Ready Engineering
Utilities and Internet Service Providers
Joint Use Make Ready Engineering
Scope of Work
- Regularly completes projects comprising of 5,000+ poles for new communication company attachments on electric utility owned poles
- Including Route design, distribution design, and distribution construction
- Currently, completing a 24,000 pole (new fiber attachment) project including:
- Field data collection
- Make ready design
- Incumbent local exchange carrier application submission
- One touch make ready administration
- Asset management work application updates
- Construction package creation
Program Highlights
- Acquired 60 complex easements, including railroad and river crossings, for a communication company build out across Pennsylvania. Additionally, spearheading a one touch make ready program for both internet service provider’s and investor-owned utilities. Increasing upfront route decisions for the internet service provider and significantly reducing application processing time for the investor-owned utility.
More Projects
Utilities
138kV Substation Expansion
Substation Engineering
Featured
345k Double Breaker Interconnect Substation
Construction Management
Utilities
Management Programs
Construction Management
Utilities
Inlet/Outlet Valve Evaluation
Natural Gas
Utilities
Odorant Replacement Project
Natural Gas
Featured
Federal Funded Maintenance Program Management
Natural Gas
Utilities
Odorant Replacement Project
Natural Gas
Odorant Replacement Project
Natural Gas
Scope of Work
- Replaced aged odorant injection system, storage tank, containment, and building at gate station
- Decommissioned and remove existing and abandoned odorant systems and associated infrastructure
- Developed and install new odorant system including shelter, piping, controls, foundations, and electrical
- Coordinated full engineering lifecycle: design, demolition, procurement support, construction oversight, and commissioning
- Executed project within defined shut-in window to maintain system reliability and operational continuity
Deliverables
- Redlined piping and instrumentation diagrams, 3D model, isometric piping drawings, construction bill of material, and valve tie-in lists
- Civil, mechanical, structural, and electrical drawings
- Demolition drawing packages with mechanical, electrical, and instrumentation and controls scopes
- Procurement packages for tank, building, odorant system, and temporary odorization
- On-site construction support, contractor coordination, and commissioning oversight
- Final documentation including updated drawings, redlines, and closeout package
Project Highlights
- The project executed a full odorant system replacement within a limited five-month shut-in window, managing the demolition of two systems in parallel with the new installation to maintain site layout. The team proactively coordinated a temporary odorization option in case of commissioning delays, provided continuous oversight from initial design through construction and as-built documentation, and supported the development of long-term record drawings and standardized site files for future reuse.
More Projects
Utilities
138kV Substation Expansion
Substation Engineering
Featured
345k Double Breaker Interconnect Substation
Construction Management
Utilities
Management Programs
Construction Management
Utilities
Inlet/Outlet Valve Evaluation
Natural Gas
Featured
Federal Funded Maintenance Program Management
Natural Gas
Utilities
Utilities and Internet Service Providers
Joint Use Make Ready Engineering
Utilities
12kV Switchgear Replacement
Substation Engineering
12kV Switchgear Replacement
Substation Engineering
Scope of Work
- Completed design to replace end-of-life 12kV switchgear
- Expanded existing yard to accommodate new switchgear and mobile substation installation
- Sited grading and stormwater controls
- Upgraded transformer protection
- 12kV underground circuit getaways
Deliverables
- Detail design and construction package
- Drawings – demolition, protection and control, physical, civil
- Studies – ground grid, foundations, substation structures
- Review switchgear vendor drawings
- Stormwater pollution prevention plan
- Construction support
- Incorporate as-built drawings post-construction
Project Highlights
- While engineering the site modifications, Orbital engineering successfully corrected existing drainage issues at the site while providing the necessary footprint for the switchgear replacement.
More Projects
Utilities
138kV Substation Expansion
Substation Engineering
Featured
345k Double Breaker Interconnect Substation
Construction Management
Utilities
Management Programs
Construction Management
Utilities
Inlet/Outlet Valve Evaluation
Natural Gas
Utilities
Odorant Replacement Project
Natural Gas
Featured
Federal Funded Maintenance Program Management
Natural Gas
Utilities
138kV Substation Expansion
Substation Engineering
138kV Substation Expansion
Substation Engineering
Scope of Work:
- Completed design to interconnect new 25MW battery & 100MW solar facility to existing substation
- Expanded existing 138kV ring bus and add one new 138kV breaker position
- Required temporary configuration of existing 138kV line to facilitate construction
- Engineered two new monopoles and one H-frame to reconnect transmission line to expanded station
- New control building with new fiber connection to support protection and controls, and telecommunications
Deliverables:
- Detail design and construction package
- Drawings – demolition, protection and control, physical, civil, transmission line with load trees
- Studies – ground grid, foundations, substation structures, transmission line structures
- Review vendor drawings for equipment, engineered structures, and calculations
- Construction support
- Incorporate as-built drawings post-construction
Project Highlights:
- Orbital Engineering navigated precise construction sequencing including temporary configurations to enable site build out while limiting downtime. Design included the relocation of existing transmission line to successfully expand the substation for the new solar and battery facility interconnection.
More Projects
Featured
345k Double Breaker Interconnect Substation
Construction Management
Utilities
Management Programs
Construction Management
Utilities
Inlet/Outlet Valve Evaluation
Natural Gas
Utilities
Odorant Replacement Project
Natural Gas
Featured
Federal Funded Maintenance Program Management
Natural Gas
Utilities
Utilities and Internet Service Providers
Joint Use Make Ready Engineering
Utilities
138kv Substation Modification To Accommodate New Generation Tie Line
Substation Engineering
138kv Substation Modification To Accommodate New Generation Tie Line
Substation Engineering
Overview
- Location: Indiana
- Client: Midwest investor-owned utility
- Timeline: 12 Months
Scope
- Design expansion of existing substation yard to the west
- Design expansion of existing 138kv ring bus to the west. add new 138kv breaker position
- Design new 138kv h-frame structure to accommodate the new incoming 138kv line
- Design transmission line interconnection from first pole outside of the substation to the new h-frame
- Perform grounding study and design grounding improvements for the substation
- Design new control building to house new relay and metering panels
- Design fiber interconnection with existing communications system
More Projects
Utilities
138kV Substation Expansion
Substation Engineering
Featured
345k Double Breaker Interconnect Substation
Construction Management
Utilities
Management Programs
Construction Management
Utilities
Inlet/Outlet Valve Evaluation
Natural Gas
Utilities
Odorant Replacement Project
Natural Gas
Featured
Federal Funded Maintenance Program Management
Natural Gas
Utilities
Water Crossing Evaluation
Natural Gas
Water Crossing Evaluation
Natural Gas
Scope of Work
- Performed condition assessments of 374 pipeline stream crossings across Indiana and Kentucky
- Utilized Trimble DA2 GPS and Esri Field Maps for sub-centimeter accuracy and real-time GIS tracking
- Evaluated water crossing conditions including erosion, bank stability, and pipeline exposure
- Coordinated land access, scheduling, and communication across a wide geographic area
- Generated Corrective Action Plans (CAPs) and prioritization based on field observations
Deliverables
- Individual field reports with exposure, erosion, and integrity observations
- Risk ranking of 43 sites with noted issues
- 3 Red: immediate action
- 7 Orange: remediation recommended
- 33 Yellow/none: monitoring recommended
- GIS dashboards and shapefiles with embedded condition data
- Sub-centimeter GPS data and photographic documentation per site
- Final report summarizing findings, lessons learned, and remediation recommendations
Project Highlights
- The project achieved 100% completion of 374 field sites within a six-month window and identified 13 new exposures along with multiple erosion and shallow-main risks. Throughout the work, the team maintained real-time communication and tracking through Esri and Trimble platforms, issued 31 CAPs to support immediate and planned remediation, and delivered geospatially enabled datasets and comprehensive documentation to support future asset planning.
More Projects
Utilities
138kV Substation Expansion
Substation Engineering
Featured
345k Double Breaker Interconnect Substation
Construction Management
Utilities
Management Programs
Construction Management
Utilities
Inlet/Outlet Valve Evaluation
Natural Gas
Utilities
Odorant Replacement Project
Natural Gas
Featured
Federal Funded Maintenance Program Management
Natural Gas
