
Utility Projects
See how Orbital supports your ability to deliver safe, reliable and affordable energy solutions to your communities.
Utilities
Odorant Replacement Project
Natural Gas
Utilities
10,000 FT Medium Pressure Steel Main Replacement
Natural Gas
Utilities
Federal Funded Maintenance Program Management
Natural Gas
Utilities
New Client Connections
Electric Distribution Engineering
Utilities
Overdue Pole Audit
Electric Distribution Engineering
Utilities
34kV Breaker Replacement Program
Substation Engineering
Utilities
161kV Transmission Line Rebuild
Transmission Line Engineering
Utilities
Management Programs
Construction Management
Utilities
Utilities and Internet Service Providers
Joint Use
Odorant Replacement Project
Natural Gas
Scope of Work
- Replaced aged odorant injection system, storage tank, containment, and building at gate station
- Decommissioned and remove existing and abandoned odorant systems and associated infrastructure
- Developed and install new odorant system including shelter, piping, controls, foundations, and electrical
- Coordinated full engineering lifecycle: design, demolition, procurement support, construction oversight, and commissioning
- Executed project within defined shut-in window to maintain system reliability and operational continuity
Deliverables
- Redlined piping and instrumentation diagrams, 3D model, isometric piping drawings, construction bill of material, and valve tie-in lists
- Civil, mechanical, structural, and electrical drawings
- Demolition drawing packages with mechanical, electrical, and instrumentation and controls scopes
- Procurement packages for tank, building, odorant system, and temporary odorization
- On-site construction support, contractor coordination, and commissioning oversight
- Final documentation including updated drawings, redlines, and closeout package
Project Highlights
- The project executed a full odorant system replacement within a limited five-month shut-in window, managing the demolition of two systems in parallel with the new installation to maintain site layout. The team proactively coordinated a temporary odorization option in case of commissioning delays, provided continuous oversight from initial design through construction and as-built documentation, and supported the development of long-term record drawings and standardized site files for future reuse.
More Projects
Utilities
138kV Substation Expansion
Construction Management, Substation Engineering
Utilities
345k Double Breaker Interconnect Substation
Construction Management
Utilities
Management Programs
Construction Management
Utilities
Inlet/Outlet Valve Evaluation
Natural Gas
Utilities
Federal Funded Maintenance Program Management
Natural Gas
Utilities
10,000 FT Medium Pressure Steel Main Replacement
Natural Gas
138kV Substation Expansion
Substation Engineering
Scope of Work:
- Completed design to interconnect new 25MW battery & 100MW solar facility to existing substation
- Expanded existing 138kV ring bus and add one new 138kV breaker position
- Required temporary configuration of existing 138kV line to facilitate construction
- Engineered two new monopoles and one H-frame to reconnect transmission line to expanded station
- New control building with new fiber connection to support protection and controls, and telecommunications
Deliverables:
- Detail design and construction package
- Drawings – demolition, protection and control, physical, civil, transmission line with load trees
- Studies – ground grid, foundations, substation structures, transmission line structures
- Review vendor drawings for equipment, engineered structures, and calculations
- Construction support
- Incorporate as-built drawings post-construction
Project Highlights:
- Orbital Engineering navigated precise construction sequencing including temporary configurations to enable site build out while limiting downtime. Design included the relocation of existing transmission line to successfully expand the substation for the new solar and battery facility interconnection.
More Projects
Utilities
345k Double Breaker Interconnect Substation
Construction Management
Utilities
Management Programs
Construction Management
Utilities
Inlet/Outlet Valve Evaluation
Natural Gas
Utilities
Odorant Replacement Project
Natural Gas
Utilities
Federal Funded Maintenance Program Management
Natural Gas
Utilities
10,000 FT Medium Pressure Steel Main Replacement
Natural Gas
345k Double Breaker Interconnect Substation
Construction Management
Scope of Work:
- Managed project construction through all phases of the greenfield build including civil work, below grade (ground grid, foundations, cable trench), and above grade (H-frame and steel erection, equipment setting, bus install, inside wiring, and incoming line stringing)
- Provided safety, environmental, and quality oversight
Deliverables:
- On-site safety audits
- Daily progress reports
- Schedule tracking and input
- Requests for Information
- Non-conformance reports
- Facilitation of material deliveries/returns
- Third-party contractor coordination
- Commissioning support
Project Highlights:
- The two-year project was delivered on budget and on schedule with strong stakeholder engagement throughout its lifecycle. With no safety incidents and multiple contractors involved across major construction phases, Orbital successfully navigated complex coordination and handoff challenges by applying deep technical expertise and maintaining strict alignment with owner processes and procedures.
View More Projects
More Projects
Utilities
138kV Substation Expansion
Construction Management, Substation Engineering
Utilities
Management Programs
Construction Management
Utilities
Inlet/Outlet Valve Evaluation
Natural Gas
Utilities
Odorant Replacement Project
Natural Gas
Utilities
Federal Funded Maintenance Program Management
Natural Gas
Utilities
10,000 FT Medium Pressure Steel Main Replacement
Natural Gas
Management Programs
Construction Management
Roles and Responsibilities
- Enforce stop work authority
- Hold construction crews accountable for compliance with owner safety processes
- Oversee execution of daily job safety briefings
- Ensure adherence to all site-specific safety and environmental plans
- Investigate and report on incidents
- Ensure required permits are maintained
- Support pre-construction planning, review drawings and bill of materials to avoid delays
- Oversee schedule performance and contribute to the development of schedule recovery plans
- Monitor construction quality by verifying compliance with drawings and specifications and preparing non-conformance reports
- Facilitate the request for information process
- Coordinate material and equipment deliveries
- Manage material inventory
- Support subcontractor assignments
- Maintain organized project records such as redlines, photos, and equipment data for final turnover at project closeout
Program Highlights
- Orbital supports investor-owned utilities throughout the country with dedicated teams of construction managers and quality management professionals. With nearly 100 boots-on-the-ground resources, Orbital’s construction management teams play a critical role in the safe and successful execution of more than $750MM in construction work annually. Through robust onboarding and continuous education programs, Orbital’s teams have the capability to support a variety of projects including new build substations, substation equipment upgrades, new build overhead transmission and distribution lines, grid modernization, underground cable replacement, overhead and underground fiber builds, and communications structure erection.
View More Projects
More Projects
Utilities
138kV Substation Expansion
Construction Management, Substation Engineering
Utilities
345k Double Breaker Interconnect Substation
Construction Management
Utilities
Inlet/Outlet Valve Evaluation
Natural Gas
Utilities
Odorant Replacement Project
Natural Gas
Utilities
Federal Funded Maintenance Program Management
Natural Gas
Utilities
10,000 FT Medium Pressure Steel Main Replacement
Natural Gas
Inlet/Outlet Valve Evaluation
Natural Gas
Scope of Work
- Performed GIS and records-based analysis of 1,617 gas regulating stations
- Evaluated compliance with inlet/outlet critical valve design standards
- Validated valve data from GIS and Maximo using spatial analysis and attribution logic
- Assigned station risk ratings based on valve presence, type, and quantity
- Developed formal reclassification, design, and investigation workflows for 1,100+ non-compliant stations
- Recommended future valve placement or conversion to critical designation using industry standards
Deliverables
- Executive summary and class 5 capital planning estimate
- G.A.C.-coded dataset with risk priority assignments
- Planning template outlining time estimates by station priority level
- Engineering design trigger list for non-compliant or undocumented stations
- Reclassification workflow diagram and phase 3 execution guidance
- GIS shapefiles for pipelines, stations, valves, and analysis overlays
- Maximo/GIS data cleanup recommendations and asset tracking integration
Project Highlights
- The team analyzed 1,617 stations across the service territory, finding that approximately 32% were compliant, 44% required formal design, and 24% were convertible through reclassification. They introduced a desktop validation and G.A.C. priority framework to streamline program actions, supported program execution with valve planning templates and phase 3 task sequencing, and applied the client’s gas standard for valve design criteria to maintain emergency access compliance.
More Projects
Utilities
138kV Substation Expansion
Construction Management, Substation Engineering
Utilities
345k Double Breaker Interconnect Substation
Construction Management
Utilities
Management Programs
Construction Management
Utilities
Odorant Replacement Project
Natural Gas
Utilities
Federal Funded Maintenance Program Management
Natural Gas
Utilities
10,000 FT Medium Pressure Steel Main Replacement
Natural Gas
Federal Funded Maintenance Program Management
Natural Gas
Scope of Work
- Lead multi-year remediation program targeting pipeline crossings, attachments, station coatings, and vehicular protection
- Developed and manage program execution for both distribution and transmission assets
- Coordinated engineering design, field documentation, and construction oversight
- Implemented phased strategy to address incomplete records, stakeholder coordination, and environmental constraints
- Updated scope to reflect evolving regulatory standards and risk assessments
Deliverables
- Engineering design packages for crossings, coatings, and protection devices
- Document control system for tracking as-builts, construction status, and compliance
- Quality assurance and quality control oversight during construction with daily/weekly field documentation
- Program tracking tools for budget, schedule, and asset-level progress
- Stakeholder communication framework to support utility, municipal, and contractor coordination
- Lessons learned and continuous improvement reports
Project Highlights
- The project successfully remediated all 23 targeted sites, and in 2024 the program expanded to include additional station coating and vehicular protection scope. The initiative supports the long-term goal of remediating over 800 assets by 2026, with an adaptable framework that accommodates evolving scope and shifting regulatory focus, providing full lifecycle support from design through construction, quality assurance, quality control, and final documentation.
More Projects
Utilities
138kV Substation Expansion
Construction Management, Substation Engineering
Utilities
345k Double Breaker Interconnect Substation
Construction Management
Utilities
Management Programs
Construction Management
Utilities
Inlet/Outlet Valve Evaluation
Natural Gas
Utilities
Odorant Replacement Project
Natural Gas
Utilities
10,000 FT Medium Pressure Steel Main Replacement
Natural Gas
10,000 FT Medium Pressure Steel Main Replacement
Natural Gas Utilities
Scope of Work
- Completed design to replace 10,000 feet of medium-pressure steel main with polyethylene (PE) piping in an urban like corridor
- Coordination with both county and municipal jurisdictions for permitting and right-of-way
- Compliance-driven design schedule to support regulatory deadlines
Deliverables
- Detailed engineering and construction drawing package
- Documentation – bill of materials, trenchless forms, pressure test forms, service orders, corrosion analysis, constructability review, environmental compliance plan
- Construction support – request for information responses, design updates, tie-in plan procedures and drawings, and permitting clarifications
Project Highlights
- The project encompassed a large scope within a dense, urban-like environment, requiring multi-jurisdictional permitting across city and county agencies. A tight compliance timeline necessitated expedited design and coordination.
More Projects
Utilities
138kV Substation Expansion
Construction Management, Substation Engineering
Utilities
345k Double Breaker Interconnect Substation
Construction Management
Utilities
Management Programs
Construction Management
Utilities
Inlet/Outlet Valve Evaluation
Natural Gas
Utilities
Odorant Replacement Project
Natural Gas
Utilities
Federal Funded Maintenance Program Management
Natural Gas
New Client Connections
Electric Distribution Engineering
Scope of Work
- Construction design of a new overbuilt double 15kV circuit
- Designed new overhead extension dedicated for new customer while maintaining operation of underground services for surrounding industrial customers
- Completed demolition of existing underground facility services and distribution equipment
- Coordinated design with customer equipment, construction and in-service dates
Deliverables
- Site visits to scope and assess constructability of underground service
- Produce a detailed design and construction package (cost estimate, design sheets, design maps, bill of materials, circuit diagram, and material reservation using client work management application)
- Coordinate easement and permit research and secure permits with local & state jurisdiction
- Create and distribute construction packets to appropriate line shops
- Provide design support during construction
Project Highlights
- Successfully achieved customer cost commitments on a expedited schedule and provided critical support to our utility partner when internal design resources were unavailable to meet the project scope and schedule.
More Projects
Utilities
138kV Substation Expansion
Construction Management, Substation Engineering
Utilities
345k Double Breaker Interconnect Substation
Construction Management
Utilities
Management Programs
Construction Management
Utilities
Inlet/Outlet Valve Evaluation
Natural Gas
Utilities
Odorant Replacement Project
Natural Gas
Utilities
Federal Funded Maintenance Program Management
Natural Gas
Overdue Pole Audit
Electric Distribution Engineering
Scope of Work
- 1549 poles were identified failing inspection but had no record of being replaced between 2015-2020
- Field audit identified poles and document findings
- Created design packets for poles that have not been replaced
Deliverables
- Report of findings from audit including, photos and checklist noting branding, inspection tags, double wood, reinforcements, and additional items
- Produce a detailed design and construction package (cost estimate, design sheets, design maps, bill of materials, circuit diagram, and material reservation)
Project Highlights
- Orbital spatially enabled a prioritized list of utility poles to assess potential replacements. A custom inspection schema was deployed in a field data collection app. All collected information was synced to a centralized GIS dashboard and database, enabling automated generation of photo reports for poles flagged for replacement, streamlining the creation of bid packages for construction teams.
More Projects
Utilities
138kV Substation Expansion
Construction Management, Substation Engineering
Utilities
345k Double Breaker Interconnect Substation
Construction Management
Utilities
Management Programs
Construction Management
Utilities
Inlet/Outlet Valve Evaluation
Natural Gas
Utilities
Odorant Replacement Project
Natural Gas
Utilities
Federal Funded Maintenance Program Management
Natural Gas
34kV Breaker Replacement Program
Substation Engineering
Scope of Work
- Replace four 34kV circuit breakers
- Adaptation to re-use existing foundation
- Replace seven disconnect switches
- New cable trench
- Upgrade bus differential relaying and transformer relaying
Deliverables
- Detail design and construction package
- Drawings – demolition, protection and control, physical, civil and structural
- Review vendor drawings for breakers, disconnect switches, and cable trench
- Material procurement support
- Construction support
- Incorporate as-built drawings post-construction
Project Highlights
- Orbital Engineering provided full engineering services for the breaker replacement program, including management of multiple sites, coordination of equipment ordering, and completion of required protection upgrades.
More Projects
Utilities
138kV Substation Expansion
Construction Management, Substation Engineering
Utilities
345k Double Breaker Interconnect Substation
Construction Management
Utilities
Management Programs
Construction Management
Utilities
Inlet/Outlet Valve Evaluation
Natural Gas
Utilities
Odorant Replacement Project
Natural Gas
Utilities
Federal Funded Maintenance Program Management
Natural Gas
161kV Transmission Line Rebuild
Transmission Line Engineering
Overview
- Location: Indiana
- Client: Midwest cooperative
- Timeline: 12 months
Scope
- Designed the rebuild of a 3-mile 69kV transmission line in PLS-CADD. The new line was designed to 161kV framing for future configurations
- Rerouted alignment in two locations to avoid river meandering and a house encroachment
- Project had three junctions with one-way and three-way switches
- Permitting, construction, and As-built support
- Plan and profile drawings, framing drawings, phasing drawings, stringing charts, staking tables, worklists, and material lists
More Projects
Utilities
138kV Substation Expansion
Construction Management, Substation Engineering
Utilities
345k Double Breaker Interconnect Substation
Construction Management
Utilities
Management Programs
Construction Management
Utilities
Inlet/Outlet Valve Evaluation
Natural Gas
Utilities
Odorant Replacement Project
Natural Gas
Utilities
Federal Funded Maintenance Program Management
Natural Gas
Utilities and Internet Service Providers
Joint Use Make Ready Engineering
Scope of Work
- Regularly completes projects comprising of 5,000+ poles for new communication company attachments on electric utility owned poles
- Including Route design, distribution design, and distribution construction
- Currently, completing a 24,000 pole (new fiber attachment) project including:
- Field data collection
- Make ready design
- Incumbent local exchange carrier application submission
- One touch make ready administration
- Asset management work application updates
- Construction package creation
Program Highlights
- Acquired 60 complex easements, including railroad and river crossings, for a communication company build out across Pennsylvania. Additionally, spearheading a one touch make ready program for both internet service provider’s and investor-owned utilities. Increasing upfront route decisions for the internet service provider and significantly reducing application processing time for the investor-owned utility.
More Projects
Utilities
138kV Substation Expansion
Construction Management, Substation Engineering
Utilities
345k Double Breaker Interconnect Substation
Construction Management
Utilities
Management Programs
Construction Management
Utilities
Inlet/Outlet Valve Evaluation
Natural Gas
Utilities
Odorant Replacement Project
Natural Gas
Utilities
Federal Funded Maintenance Program Management
Natural Gas
